Electronic controlled bottom loading skid supplied to Carrs Billington, Cockermouth UK Depot

OVERVIEW: Carrs Billington is one of the largest authorised oil distributors in the UK & currently covers the North of England & South of Scotland. They supply a wide range of fuel and lubricant products to homes for domestic, farms for agricultural and commercial use  to customers. Carrs Billington operate as Johnstone Wallace Oils in South West Scotland, Wallace Oils in North Cumbria and Carrs Billington Fuels around Lancaster, Northumberland and West Cumbria. IFC Inflow were asked to supply an electronic skid for safe tanker loading to a new depot as part of an ongoing depot upgrade and development programme.

SITE: Cockermouth, Cumbria, UK – New build oil distribution depot

IFC SOLUTION: The main goal of the project was to provide a fast and safe tanker loading system to allow an increase in sales of their fuel products. A safe tanker loading skid with electronic controlled bottom loading arms was suggested by IFC. They also recommended bulk flow meters with flow rates of up to 1200 l/min, fitted with the latest 5 point skid safety system.

For monitoring and controlling the fuel stock being loaded through the skid, MHT Terminal Automation software was installed for complete depot automation.

MHT VTW tank gauging system allows accurate stock reconciliation both locally and by remote link to head office. High level tank alarms & digital field displays were fitted for added depot safety. Tank gauging was made easy by implementing this system for monitoring oil and fuel stock levels in bulk storage tanks at the depot.

Three 70,000 litre over ground, double skinned bunded, bulk fuel storage tanks for Diesel (Derv), Gas Oil and, Kero tanks with a separate lockable fill cabinet allowing simultaneous loading & delivery operations were placed on site as storage tanks. They had 110% secondary containment area built into the tank and were built to Control of Pollution Regulations which require a Design Life Expectancy of 20 years, and OFTEC OFS T200 certificates.

IFC provided all site mechanical and electrical works along with full equipment commissioning.

PROJECT OUTCOME:
Successfully supplied and installed on time and in budget allowing the depot to open before the busy winter period. The new equipment now provides faster tanker loading up to 1200l/min combined with greater depot and operator safety with more accurate stock control systems.

“Our depot is up and running within the projected timescale and we could not be happier with the outcome of the project”
– Nigel Hiller, Carrs Billington

Do you want more information?

  • Image Gallery

    By continuing to use the site, you agree to the use of cookies. more information

    The cookie settings on this website are set to "allow cookies" to give you the best browsing experience possible. If you continue to use this website without changing your cookie settings or you click "Accept" below then you are consenting to this.

    Close