Many of our customers are currently investing in new equipment and infrastructure to support Future Fuels. One such project involved UM Terminals, who approached us for an HVO loading solution in the form of a single-arm skid.
Project Requirements
From the outset, the customer prioritised efficiency. Therefore, the solution needed to deliver high flow rates and reduce tanker loading time.
Our Recommended Solution
To meet these requirements, IFC Inflow recommended a 4” Electronic Bottom Loading Skid. This system delivers flow rates of up to 1500l/m, allowing a 36,000-litre tanker to be filled in less than 30 minutes. This skid provided a reliable HVO loading solution aligned with the customer’s efficiency goals.
Delivery and Installation
UM Terminals managed the installation themselves. To keep the project moving, we delivered the equipment well within the 12-week lead time. This helped the customer stay on schedule and get up and running as quickly as possible.
Outcome
As a result, UM Terminals can now accommodate HVO on site while achieving high flow rates and faster loading times.
If you’re upgrading your site for HVO or other future fuels, contact us to discuss the right loading solution for your operation.